Geotechnical Investigations

Karot Hydropower Project in Pakistan

2018-12-04T08:25:46-05:00Geotechnical Investigations, IVCC CPEC PROJECTS|

Karot Hydropower Project  Scope of Work: Geotechnical Investigation IVCC was involved in drilling of 13 Boreholes with depths from100-130 meters, using Straight Rotary Machines in weathered and fresh rock obtaining continuous samples using double tube coring equipment. Total drilling footage for 13 Boreholes was 1,690 meters. IVCC drilled 3 Boreholes on dry land with

Geological Investigation Work Mahl Hydropwer Project in Pakistan under CPEC 2016

2018-10-16T14:01:14-04:00Drilling, Geotechnical Investigations, IVCC CPEC PROJECTS|

Mahl Hydropwer Project in Pakistan: Proposed 590 MW on Jhelum River & Mahl River at the border of AJ&K and Punjab Province: Boreholes Drilling for Geological Investigation Work. Scope of Work: Drilling of 52 Nos. Boreholes Land Drilling (vertical& inclined) upto maximum depth 235 meters (Land & Submerged Drilling). Total drilling carried out 5,098 meters.

Kohala Hydropower Project under CPEC (District Muzaffarabad, Pakistan) 2016

2018-12-06T13:56:35-05:00Drilling, Geotechnical Investigations, IVCC CPEC PROJECTS|

Geotechnical Investigations in Pakistan IVCC drilled 4 Boreholes, ZKT-4 (Dia. P/H/N/B), ZKT-5 (Dia. H/N), ZKT-6 (Dia. H/N) and ZKC-15 (Dia. H/N). These had a maximum depth of up to 400 meters. Total drilling footage for this phase was 1,325 meters. IVCC carried out Rotary Drilling to recover cores from soil, weathered and fresh rock. All

Azad Pattan Hydropower Project under CPEC (Jehlum River, Pakistan) 2017

2018-12-06T13:50:28-05:00Drilling, Geotechnical Investigations, IVCC CPEC PROJECTS, Recent Projects|

Geotechnical Investigation & Adits Work in Pakistan Drilling of 2 Boreholes ZKC-1 (70 Meters) and ZKC-2 (45 Meters) on Jhelum River. IVCC Carried out Carry out 20 water pressure tests and 2 water injection tests (Total drilling 115 meters). Drilling of 11 (ZKY-1 to ZKY-11) Rotary drill holes on dry land both vertical and

Maple Leaf Cement Factory Geo-technical Investigations

2018-10-17T09:49:13-04:00Geotechnical Investigations, Recent Projects|

Maple Leaf Cement Factory – Iskanderabad, Mianwali District – Pakistan (2017-2018) IVCC Engineering Pvt Ltd executed Geotechnical Investigation works for Maple Leaf Cement plant, one of Pakistan’s largest cement factory. The work was conducted in various phases. A total number of 55 boreholes (max depth 45 meters) were drilled, using rotary drilling equipment. 1,794